Activity Report: Work Period Beginning December 9, 2019

This post is an overview of the work undertaken by God’s Way Ltd, during the work period December 9th – 20th, 2019. Activities for this period include: Director Activities Heavy Machinery Maintenance Dam Earthworks Removal of Fences Safety Equipment Maintenance…

Read More

Function Centre Caretaker’s Residence Renovation: Insulation & External Cladding

Under the direction of Jesus (AJ Miller) and management of David Walsh (Cornelius), the God’s Way Ltd Construction Team has continued work on the Cushnie Function Centre Caretaker’s Residence Renovation Project. During June 2019, God’s Way volunteers insulated the walls…

Read More

Notice Board: Free Fencing Materials-Self Removal – No Longer Available

No longer available Hello! There are approx 1800 metres of fencing materials that need to be completely dismantled & removed from the God’s Way Ltd Function Learning Centre Caretakers property in Cushnie, Queensland Australia (photos below). These materials are yours for…

Read More

Volunteer Selection: Reminder Registrations Close 5th January 2020

Hello! This is a reminder that registrations for the Volunteer Selection Programme (VSP) are closing on the 5th of January 2020. If you would like to be a participant in the next VSP please register your interest at the God’s…

Read More

Garden Design: Cushnie Function Centre Caretaker’s Residence

During the Volunteer Selection Project (VSP) held during April 2019, participants contributed to an activity of God’s Way Ltd Environment Branch, which involved preparing an area of the Cushnie Function Centre Caretaker’s property for creating a garden. Positioned between a…

Read More

Function Centre Caretaker’s Residence Renovation: Making the Changes

Welcome to the next update on the Cushnie Function Centre Caretaker’s Residence Renovation Project. The Team has begun some construction at last. Renovations are interesting in that you have to remove everything that’s not needed in a de-construction phase, before…

Read More

Activity Report: Work Period Beginning November 18, 2019

This post is an overview of the work undertaken by God’s Way Ltd, during the work period November 18th – 29th, 2019. Activities for this period include: Project Planning Heavy Machinery Maintenance Dam Earthworks Terraces Project Safety Equipment Maintenance Cushnie…

Read More

God’s Way Ltd 2019 Annual Report

Directors’ Message – Extract from God’s Way Ltd 2019 Annual Report One of God’s Way Ltd’s aims is to discover and demonstrate effective methods in harmony with God’s Laws; which can be employed by any willing and passionate person, in…

Read More

Technical Training: An Introduction to HTML

The purpose of the God’s Way Ltd Technical Training Programme is to create training resources for a variety of technologies, which can be used within the organisation and shared publicly. In setting up Divine Truth Pty Ltd, God’s Way Ltd…

Read More

Project Update: Experiments with Suppression of Mother of Millions

Mother of Millions Plant From 2018, God’s Way Ltd volunteers have been involved in the removal of the introduced species Mother of Millions on the private property of the God’s Way Ltd Founding Members. Mother of Millions is an ornamental…

Read More